VoltGrid S.r.L Completes Transformer Installation and Commissioning in Germany
VoltGrid S.r.L has completed the installation and commissioning of a 63.5 MVA – 115/31.5 kV BEST Transformer at a substation in Germany. The project involved mechanical assembly, internal inspections, vacuum oil treatment, controlled oil filling, and electrical testing using equipment including Doble M5500 and OMICRON TESTRANO 600.
The transformer was installed and commissioned in compliance with industry standards to ensure reliable operation. The work was carried out in coordination with BEST Transformer and included all necessary procedures for mechanical, electrical, and functional readiness.
The project adds to VoltGrid S.r.L’s portfolio of transformer installation and commissioning projects in Europe.