Media Hub

Media Hub

Media Hub

Podcasts

Webinars

Tech Talks

Power Panels

CEO Forums

Technology Showcases

Event Interviews

Other Brands

Trustworthy coverage of the transformer and transformer-related industries.

Visit Website

Trustworthy coverage of the transformer and transformer-related industries.

Visit Website

Leaky part delays transformer installation in Boulder City

4 Apr 2019

NEVADA - Installation of Boulder City's new back up transformer, which was delivered almost a year ago, has been delayed until October due to a faulty part, reports Boulder City Review.


A leak in the new transformer which was delivered to Boulder City in April 2018 was discovered in July, and the staff contacted the manufacturer about it.

"One of the manufactured parts needed to be replaced with a new manufactured part, which took several weeks to complete," said Lisa LaPlante, the city's communications manager. "Once the manufacturer received the part, the city was notified the part was incorrect and another one had to be manufactured."

The new part was installed and successfully tested in January.

The new backup transformer, which is expected to increase the reliability of the city's electrical system, is now expected to be operational in October.


Source: Boulder City Review

Lightning bolts strike across a dark blue night sky.

Subscribe to our Newsletter

Subscribe to our newsletter and stay ahead with the latest innovations, industry trends, and expert insights in power systems technology. Get updates on cutting-edge solutions, renewable energy advancements, and essential best practices delivered straight to your inbox.